Government confirms construction products reform regime – what you need to know
NFRC engaged with trade and supplier Members through meetings and a webinar, which was attended by representatives from MHCLG. The webinar provided over 80 NFRC Members with an opportunity to learn about the proposals and contribute to NFRC's consultation response.
On 18 November, the government published its response to the Construction Products Reform White Paper consultation. It confirms the direction of reform and how it will be delivered. Much of the detail is still to be settled.
This article covers
- what has been confirmed,
- how it compares with NFRC's consultation response,
- and what happens next.
The government plans to legislate from 2027, phase the changes in, and move the regulator's role into the new single construction regulator over time.
NFRC supported the aims of reform, and many of the principles we supported are in the response. Certain issues that mattered to our members during consultation are not yet settled. These include discussions on liability, testing capacity, and timing.
What the government has confirmed
- No list of "critical" products. The government will not create a statutory list. It will instead review Building Regulation 7(1) and Approved Document 7, which cover how products are selected and installed safely.
- Two regimes. Products with a designated standard or technical assessment stay under the construction products regulations (CPR). All other products come under the General Safety Requirement (GSR). A product sits under one or the other, not both. The regulator can remove unsafe products under either.
- Licensing for testing and certification bodies. All UK conformity assessment bodies (CABs) will need a licence from the national regulator.
- Whistleblowing protection. Workers who report construction product concerns to the regulator will have legal protection.
- Public testing capacity. The government is committed to it but is still weighing up options. Don't expect anything on this for a while.
- Timing. The government intends to lay the GSR regulations in 2027. They will come into force no earlier than 12 months later. The new GB-CPR is expected in 2028 for products with standards developed under the new framework. Other products stay under the current rules until a new standard is adopted.
Where the response reflects NFRC's position
- No fixed product list. We argued that criticality should depend on end use and risk of failure, not product category. The government agrees. Our members were split on the application of these settings. About half said all roofing and cladding components should be treated as critical, so we will watch how it works in practice.
- CAB licensing. We backed a mandatory regime with clear criteria, proportionate requirements and public licence information. All three are confirmed. CABs can also use UKAS accreditation as evidence in their licence application, which should help to limit duplication.
- Whistleblowing. We supported legal protection for people who report concerns. The regulator will become a prescribed body for these reports. CABs will have to run internal whistleblowing processes as a licence condition.
- Accountability. We said responsibility should sit with whoever controls a decision. The government has adopted this principle. It will also develop worked examples and responsibility matrices.
- Support for SMEs. The government commits to clear guidance, communications and phased implementation aimed at smaller businesses.
Where we have concerns
- Contractor liability is not yet settled. The government says extra assurance on installation is best handled through building regulations. The government's review of Building Regulation 7(1) of the Building Regulations 2010 and Approved Document 7 will look at the duties of specifiers, designers, contractors and installers. That could place new duties on contractors. The response does not confirm our position that contractors should not carry responsibility for a product's intrinsic safety or for design decisions made without them. It also does not deal with substitutions where no principal designer has been explicitly appointed.
- Timing. The earliest GSR start is now 2028 rather than late 2027. That is an improvement, but it is not the late 2028 we asked for. We wanted guidance published at least 12 months ahead to ensure businesses can get ready. The government promises guidance "sufficiently ahead" of commencement but sets no fixed lead time. Many of our members asked for at least 24 months.
- Cost and regulator capacity. We said regulator resourcing must be a precondition for reform. The government says costs will be proportionate and capacity will be central to delivery. It makes no specific funding commitment.
Worth monitoring
- The Regulation 7(1) and Approved Document 7 review. This is where contractor and installer duties are likely to be set. We have called for mandatory installer competency to be reflected here. Guidance and worked examples. We want clear rules on where a manufacturer's advice becomes design responsibility, on product substitution, and on assessing roof and cladding systems as a whole, including retrofit and solar PV.
- Competence. Government is developing a baseline expectation of competence, alongside a forthcoming Building Professions Strategy.
- Product information. The government will not take forward a construction product library until underlying data problems are fixed. It is exploring digital product records. We would like to see new requirements fit with the Code for Construction Product Information, so that already compliant manufacturers do not duplicate effort.
What next Manufacturers and merchants. Check whether your products have a designated standard or technical assessment (CPR) or not (GSR). Review your test evidence and product information. Distributors, including merchants, will have obligations under the GSR.
Contractors. Nothing changes today. Keep following manufacturers' installation instructions and make sure any product substitution is documented and approved.
If you have views on any of these areas, send them to [email protected]. They will help shape how NFRC engages government and develops guidance the reforms progress.
Read NFRC's response to the consultation.